your commute to HITEC City and Financial District is just a 15 to 17 minute drive on the Nehru outer ring road
Sprawled across 25 acres, this vibrant gated community offers 14 towers in total, 13 of which have already been delivered. PBEL CITY located away from the city but still near everything important.
Every floor has early warning fire measures like hand-held extinguishers and water hoses.
In case a fire is too intense for early warning fire measures, follow the exit signs and evacuate the building.
A pressurized network of pipes feed the fire sprinklers in every room of your house.
Every fire sprinkler has a temperature activated glass bulb that melts at 68° Celsius.
Only the fire sprinklers in the region of the fire will activate when a fire melts the glass bulbs.
Temperature Activated Sprinkler
Three redundant water pumps activate in sequence when they sense a drop in water pressure. This ensures the sprinklers are fed with a constant water pressure.
Pump 1 is an electric pump capable of delivering 180 litres per minute.
Pump 2 is a high capacity electric pump which can deliver up to 2250 or 2850 litres per minute, depending on the height of the building. This pump switches on if Pump 1 is unable to maintain water pressure.
Pump 3 is a high capacity diesel pump which can also deliver up to 2250 or 2850 litres per minute, depending on the height of the building.
This diesel pump switches on if Pump 1 and 2 are unable to maintain water pressure or if the electrical power supply fails.
68°celsius
will melt the temperature activated glass bulb and active the sprinkler.
Engineering
The engineering that ensures your water comes to you at the right quality and pressure.
Treatment and reuse of Sewage Water drops the overall quantity of water needed by a factor of 40.9%.
Metered water usage on an apartment level reduces water consumption patterns.
Low flow, water-efficient fixtures imitate the flow characteristics of regular fixtures while using 30% less water.
Pneumatic Booster Pumps actively boost water pressure to the upper floors.
Pressure Reducing Valves are passive mechanisms that reduce water pressure across lower floors.
Pressure Reducing Valve
Construction
Updates
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
April 2020
March 2020
February 2020
January 2020
Lakeside Update
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Entrance Lobby Italian Marble flooring & Granite steps, ramp and planter box completed & False Ceiling works in progress. Stilt floor VDF flooring works in progress. 2nd coat painting works completed from 2nd to 15th floor. Corridor false ceiling completed upto 30th floor. Corridor ceiling putty works completed up to 22nd floor and remaining work in progress. Corridor 1st coat paint completed up to 22th floors and remaining work in progress. Corridor tile grouting completed up to 18th floor and remaining floors in work in progress. Flats tile grouting completed up to 20th floor and remaining work in progress. Internal door shutter fixing completed up to 20th floor and hardware fixing completed up to 17th floor. External painting works in progress. Service lift Commissioning works in progress. P3&P4 lift Installation work in progress. P1&P2 Lift Electrical work is completed. Stilt Floor corridor area sprinkler installation work is completed. BASEMENT Painting works in progress. Gas Bank plinth Beams and grade slab casting completed and diaphragm wall work in progress. Basement Pump room flooring work in progress. Transformer yard slab, wall, steps casting completed.
Lakeside
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Entrance lobby Italian marble flooring & wall tiling works in progress. Staircase kota flooring completed. Staircase 01 & 02 1st coat paint completed from 1st to 30th floor. 1st coat painting works: Completed up to 29th floor. 2nd coat painting works : Completed from up to 11th floor. Corridor false ceiling: Completed up to 25th floor. Toilet Grid false ceiling: completed up to 20th floor. Flats tile grouting completed up to 20th floor and remaining work in progress. P3 & P4 lift cladding completed up to 30th floor. Flats tile grouting completed up to 20th floor and remaining work in progress. Internal door shutter fixing completed up to 17th floor and hardware fixing completed up to 11th floor. Main door shutter polish work in progress. Sanitary fixing works completed up to 20th floor and remaining work in progress. Flats internal wiring completed up to 23rd floor and Remaining work in progress. Service lifts & Passenger Lifts installation work in progress.
Lakeside
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Unit-04 Lobby blockwork completed, false ceiling work in progress. Main Door Shutter Fixing upto 25th floor completed, Main Door Shutter Fixing upto 25th floor completed. Service Lift Cladding Completed., P3 & P4 lift Cladding Competed up to 25th floor and remaining work in progress. Staircase 1: putty works completed, Staircase 1 : Kota stone polishing works in progress , Staircase 2 : putty works & Kota stone polishing works completed. Balcony railing painting work in progress. Corridor false ceiling: 20 floors completed; sanitary fittings completed till 16 floor. Corridor wiring work completed till 21st floor. smoke detectors installation completed till 20th floor in flat. Switch bords installation completed till 20th floor. Sprinkler installation completed till 21th floor. EXTERNAL Podium North-East corner concrete casting completed. Podium water proofing completed on South east side.
Lakeside
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
External painting works in progress. Basement Painting works in progress, External chamber works in progress, Terrace water Proofing works In Progress. Main Door Frames installation completed at 30th floor. 1st coat painting works completed till 28th floor. Lift installation works in progress, Electrical 7 Communication shafts white washing completed. Staircase Kota stone Polishing and putty works in progress. Corridor false ceiling completed till 16th floor. Pump rooms works in progress
Lakeside
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Door Frames installation in progress at 30th floor, Corridor Flooring completed at 30th floor, Staircase Windows installation completed at 30th floor, 2nd coat painting works completed till 9th floor, Corridor False Ceiling works completed till 13th floor, Toilets False ceiling works in corridor completed till 12th floor, External painting works in progress, Fire Pumproom works in progress, Electrical works in progress in 13th & 20th floors, Lift installation works in progress. External: Drain wall casting works in progress at podium, North podium Waterproofing works in progress, Basement east side grade slab completed, Terrace water proofing works in progress.
Lakeside
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Terrace LMR Blockwork completed, Terrace brickbat works in progress, Balconies & Utilities Waterproofing at 22nd floor in progress. Main door shutters fixing is in progress at 20th floor. Sliding doors installation is in progress at 24th floor. 1st Coat painting work in progress in 26th floor. Pelmet works in progress in 16th floor. External Painting works in progress. Fire pumps installation works in progress
Lakeside
Tower M
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Unit no 4 & 7 OHT casting completed. South side podium side final slab casting completed. Lift shaft surface preparation & white wash works in progress. Terrace unit no 1 & 10 initial ponding testing works in progress. 21st floor utilities & balconies waterproofing works in progress.30th floor toilet tiling works in progress.26th floor 1st coat painting works completed. Unit no 9 west side texture works in progress. Basement fire fighting works in progress. Basement Footprint area grade slab completed
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
TOT- LOT area all works completed.
Lakeside
Tower M
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
External paint east side works in progress. South side non tower area PCC works in progress . Basement Footprint area grade slab casting completed for 7 units. LMR Blockwork in progress. Service & P4 lifts final coat white wash completed. 29th floor flats tiling works in progress.20th floor UPVC Sliding doors fixing works in progress. 30th floor internal firefighting & PHE works completed.
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
Kids play area equipment installation completed. Plantations works in progress. North side car parking sheds framing & painting works completed.
Lakeside
Tower M
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Lift 1 OHT Bottom slab and LMR bottom slab reinforcement work in progress. Podium level soil dressing & Pump room staircase head room works in progress. 10th floor balconies waterproofing works, 27th floor putty and tiling works,12th floor pelmet works in progress and 10th floor internal flats wiring in progress.
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
TOT LOT granite flooring works completed ,TOT LOT electrical poles fixing works in progress and North side car parking sheds framing & painting works completed.
Lakeside
Tower M
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Terrace level slab completed.Unit 5 swimming pool bottom slab,Balconies waterproofing works, Door frame fixing works,putty works in progress. Toilet dado & tiling 26th floor and Corridor flooring 24th floor works in progress, Staircase 1 & 2 Kota stone 12th floor in progress.10th floor corridor wiring & 6th floor DB Dressing works in progress.
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
TOT LOT fabrication works completed, Granite flooring works in progress and North side car parking shed works in progress.
Tower M
Lakeside
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
All works completed till the 18th floor. On other floors, in-progress are works related to the main door polishing, paint, electrical wiring, CP & Sanitary fixing, AC copper cable routing, Tot-lot pergola and water-proofing.
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Structure completed till the 29th floor. In progress are different works like putty works, kota stone laying on the staircases, main door shutter along with digital lock fixing, sliding doors fixing, toilet daddo & tiling, internal apartment tiling & tile protection and other internal works. The mock-up apartment is ready for viewing.
Tower M
Lakeside
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
External paint completed alongwith the lobby marble polishing works, DG room fabrication works and the north side exit gate works. In progress are works related to the main door polishing (above 19th floor), 2nd coat paint (completed up to 18th floor), electrical wiring and CP & Sanitary fixing (done till the 17th floor).
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Structure completed till the 28th floor. In progress are different works related to balconies & utilities railing (at the 25th floor), door frames fixing (at the 21st floor), UPVC windows fixing (at the 7th floor), apartment & corridor putty (at the 17th floor), inside apartment tiling (at the 19th and 20th floor) and fire fighting testing works (at the 24th floor). For the mock-up apartment, all interior (wood work) and final painting works are completed.
Lakeside
Tower M
Tower N
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Structure completed till the 26th floor. Putty works are in progress on the 13th and 14th floors along with toilet dado & internal apartment tiling on the 17th floor. The fire fighting works are in progress on the 23rd floor.
TS RERA Number: P02400001909
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower M update
Final coat (2nd) of external paint in progress. Works are also in progress for the main door polishing (above 19th floor), 2nd coat paint (completed up to 16th floor), basement & staircases (Kota stone) polishing, corridor final coat painting and lobby tiling polishing works are in progress. Electrical wiring till the 18th floor and CP & Sanitary fixing till the 16th floor are completed.
TS RERA Number: P02400000676
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower N update
Works are in progress for the Car Park Sheds while the Tot-lot area's water flooring works are completed.
Lakeside
Tower M
Tower N
TS RERA Number: P02400003490
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Lakeside Update
Structure completed till the 24th floor. Putty works are in progress on the 11th and 12th floors. While door frames fixing is completed up to the 15th floor, toilet dado & internal apartment tiling works are in progress on the 15th floor. The fire alarm and detection system conduit laying works on the 22nd floor are in progress.