Comprising 2 & 3 BHK apartments in Kondapur, with Phase I ready to move in and Phase II under construction.
With easy access to, Education, Healthcare, Recreation, Office Workspaces and more; you are surrounded by life but you can still pull back at the end of the day from this hustle and bustle to give time to yourself and your family!
Or, if you'd like a copy of the physical brochure couriered to your location. Click Here
Engineering
Built with precision moulded concrete structures to ensure factory-like repeatable quality in each home.
Shear Wall Engineering
The monolithic structure is stronger, has a longer life and is more earthquake resistant.
Unified build process. Structure, walls, electrical and plumbing are installed and built simultaneously.
No need for plastering because the wall surface is smooth and precise.
Pleasing and functional interior walls that don’t have visible beams and columns.
The factory-like repetitive ‘build and check’ process ensures predictable quality.
Concrete is an excellent insulator. Our buildings are cooler and have better sound insulation.
Construction Partner
Material Brands Used
Structure
Finishes
Plumbing
Electrical
Fire Safety
Masterplan and Floorplans
Masterplan
Floorplans
Rotate device for best experience!
Tower A
Tower B
Tower C
Tower D
Rotate device for best experience!
Rotate device for best experience!
Rotate device for best experience!
Rotate device for best experience!
Amenities
Clubhouse
Other
The Square - Clubhouse
Swimming Pool
Gymnasium
Salon space
ATM space
Multipurpose Hall space
Party Hall space
Café’ space
Creche space
Supermarket space
Squash court
Badminton court
Table Tennis
Spread Across the Project
Tennis court
Half Basketball court
Cricket Net
Children’s play area
Cycling track
Meditation area
Gazebo
Banquet lawn
Multipurpose lawn
Engineering
Every balcony railing has vertical divisions. This ensures that children cannot climb them.
Safety Engineering
Depending on the height of the building, 1.1m to 1.2m high balcony railings ensure safety on any floor.
Apart from a few horizontal railing members that are a structural requirement, all other railing members are vertical.
Compliant with the Bureau of Indian Standards National Building Code.
Bureau of Indian Standards
Construction
Updates
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
Tower B
Tower C
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
Structural works 19th floor slab completed and 20th floor slab in progress. CPVC Routing completed upto 17th floor. PVC Routing completed upto 15th floor. Toilets water proofing completed till 11th floor, Balcony Railings completed till 12th floor,Toilets Dado & Tiling completed till 11th floor, Flat tiling works completed till 11th floor,2nd coat Putty completed till 7th floor, Installation of UPVC completed till 11th floor
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
Toilet Tiling Works completed from 2nd to 17th floor. Floor tiling works completed upto 16th floor. 2nd Coat Putty completed from 2nd floor to 19th floor. Shaft doors installation completed from 2nd floor-10th floor. Staircase-1 Doors completed from 2nd to 10th floor. UPVC Doors Completed from 1st floor-15th floor. Sliding doors Completed from 10th to 15th floor. Windows completed from 1st to 22nd floors. Corridor False Ceiling framing completed upto 20th floor. Service lift Bulkhead lighting completed. Lifts installation works in progress. CPVC Routing completed upto 21st floor. PVC Routing completed upto 19th floor. Fire Fighting Riser line completed upto 21st floor.Terrace water proofing works 3/8 units completed.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
BASEMENT: Exit Ramp (B1-Podium) screed work completed, Painting works in progress. EXTERNAL: Kids Play area – 2 (South side) 100% works completed and handed over to residents. Open Gym Led Lights installation completed and EPDM works to be started. Fencing works Badminton court, Half Basketball & Cricket nets Led Lights 100% installation completed, Chain-link Fencing 95% completed, Cricket net works in progress, Sports flooring works to be started. Boundary wall fencing completed for Phase - I. Security Cabin Plastering & Painting completed. Entrance Portals Installation in progress. Bus Bay Portals installation completed and civil works in progress. Podium Water proofing + Screed East & North side to 70% completed . Exit Ramp Cover Slab Exit Ramp Top slab and parapet wall casting completed.
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Handovers in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
Structural works 19th floor slab in progress and 18th floor slab completed. CPVC Routing completed upto 16th floor. PVC Routing completed upto 14th floor.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
Floor tiling works completed upto 15th Floor and 16th is in progress. Toilets Tiling works completed from 2nd floor-16th floor. Wall Putty works – 1st Coat Putty: completed from 2nd floor – 18th floor. Shafts White washing : All Corridor Shafts completed. Corridor False Ceiling completed upto 20th floor. Lift Shafts: Service lift White wash completed, Passenger lift -1 & 2: White wash completed. CPVC Routing completed upto 20th floor. PVC Routing completed upto 18th floor. Fire Fighting Riser line completed upto 16th floor. Basement Entrance lobby blockwork is in progress. Terrace Water Proofing Surface Preparation works is in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Handovers in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
BASEMENT Basement – Fire Fighting lines Fabrication & Erection Basement – 1 & 2 in progress. CLUB HOUSE Club House inaugurated on 20th July 2024. EXTERNAL Phase I: Kids play area opened for residents. Open Gym : Granite works 100% completed. Kids Play area – 2 (South side) Equipment installation Completed; Screed & EPDM works to be carried out. Entrance gate : Security Cabin Plastering & painting completed, Entrance Portals Installation in progress Phase II: Podium Water Proofing East Side Surface Preparation in progress. Exit Ramp Cover slab Shuttering works completed
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Handovers in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
18th floor slab in progress. Putty works completed till 5th floor. Tiling works completed till 5th floor. Tower – B around Non – Tower area – 100% completed. Exit Ramp Wall Rebar works in progress; Cover slab to be cast.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
Wall putty works in progress in 16-17 floors. Tiling works completed till 15th floor.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Handovers in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
CLUB HOUSE: Painting and Deep Cleaning works completed. Indoor Games room ready, Gaming Equipment Received. Toilets Cubicles installed and cleaning Completed. CP & Sanitary Installations completed. Wash basin above Mirrors & Lights to be installed. Badminton & Squash Court Ready. Terrace Ramp SS Railing completed. Multi – purpose hall cum Yoga room Vinyl Flooring & Mirror Installation completed. Super Market area – Ready for Vendor move-in. Water Filling in Pool & Balancing tank completed. Filtration in progress. EXTERNAL: West side Kids Play area – 100% completed. Tennis Court & Half basket ball court – WMM Spreading completed; Rolling works to be started. Entrance Gate MS Portals Installation works in progress. Temporary Safe access at Podium for Pedestrian walk way.
Tower A
Tower B
Tower C
Tower D Update
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Handovers in progress, Entrance Lobbies are ready and Corridors cleaning in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
16th floor slab completed, 17th floor slab works in progress, Plumbing works in progress in 19th floor, Fire fighting works in progress in 14th floor
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
External painting works in progress, Tiling works in progress, Plumbing works in progress in 19th floor, Staircase Railing works completed, Fire Fighting works in progress in Basements, Corridor Fire line completed in 22nd floors
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Handovers in progress, Entrance Lobbies are ready and Corridors cleaning in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
External: Podium Lights installed, CC Cameras installation completed, Play courts fencing works in progress, Transformer & DG Yard fencing works in progress, Open Gym equipment installation completed, Transformer yard commissioning works completed. Clubhouse: External painting completed, Badminton court flooring works in progress, Entrance glass works completed for squash court, Lighting works for Banquet hall completed, Toilets cubicles installation completed, Gym Equipment installation in progress, Mirrors installation in progress, Swimming pool works completed, water filling in progress, Parapet & Deck Glass railing works in progress. Basements: Car Parking markings and Numbering in progress, Signage Boards installation in progress.
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Handovers in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
15th floor slab completed, 16th floor slab works in progress, Plumbing works in progress in 9th floor.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
External painting works in progress, Tiling works in progress, Plumbing works in progress in 19th floor
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Handovers in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
CLUB HOUSE: Badminton Court – Wooden Flooring works completed, 2nd coat painting works completed, Squash court painting works in progress; Railing works completed, Terrace Granite works in progress, Internal False Ceiling works in progress. EXTERNAL: Kids play equipment installation completed, DG Exhaust works completed, Cobble stone works completed.
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Handovers in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
15th floor slab structural works in progress. 1st floor Flat tiling works in progress 4th floor CPVC lines works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
Above Terrace works in progress. External painting works in progress on North side.11th & 12th Floors corridor false ceiling framing works in progress. 10th & 11th Floors putty works in progress Flat & balcony tiling – 9th floor works in progress. Toilets tiling – 12th floor works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Handovers in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
CLUBHOUSE: Banquet Hall False Ceiling works completed (incl. Putty & Primer). 2nd Floor Gym area 3rd coat putty works completed. 3rd Floor Badminton court HVAC ducts & Ceiling painting works Completed. Indoor Games 3rd coat putty works completed. Terrace Trellis installation completed. Club house entrance lobby staircase granite works in progress. Club house around plantations works completed. Club house around plantations works completed. EXTERNAL: Club house north side cobble stone work completed. South side screed works Completed. Club house west side VDF works completed. North side Non tower area – B1 slab works in progress. Central lawn area plantations work in progress North side Retaining wall works in progress.
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Flat Handovers in progress. Main doors installation completed & 19th to 22nd floors internal doors installation works in progress.19th to 22nd floors kitchen dado works in progress.19th to 22nd floors copper piping works in progress. Terrace waterproofing Final Finishing works in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
12th floor slab casting works completed and 13th floor slab casting works in progress. 1st floor flat tiling in progress.4th floor PHE works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
22nd floor & terrace level slab casting completed and LMR OHT works in progress.11th & 12th floors corridor false ceiling framing works in progress.10th &11th floor putty works in progress.8th floor Flat & balcony tiling works in progress and 11th floor toilet tiling works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Flat Handovers in progress. Main doors installation completed & 19th to 22nd floor internal doors installation works in progress.21st to 22nd kitchen granite floors works in progress.18th to 22nd floors copper piping works in progress. Entrance lobby area railing works completed. Terrace waterproofing Final Finishing works in progress
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
CLUB HOUSE Banquet hall flooring completed and false ceiling works in progress. Entrance lobby area tiling works completed, false ceiling works in progress. 3rd floor balcony area tiling & railing works completed. Ramp area granite works completed. Banquet hall around hardscaping works in progress. Squash court wooden flooring fixing works completed. Terrace trellis works in progress. EXTERNAL Podium level landscaping & plantations works in progress. Tower D around screed works 95% completed. Tower A around screed works 95% completed. East side & central lawn area pergola installations work in progress. Club house front side cobble works in progress.
Tower A
Tower B
Tower C
Tower D
Common Area, Basement & Clubhouse
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Wooden rafters’ installation works completed and Primary Polishing works for Marble flooring completed.19th to 22nd floor door fixing works in progress.18th to 20th copper piping works in progress. Handovers in progress. Kitchen granite works completed up to22nd floor except 10 & 11 units. 1st coat external paint completed.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
9th floor slab casting works completed & 10th floor slab casting works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
Terrace level slab casting completed. 8th floor flat tiling works in progress.9th floor CPVC lines works & PVC hanging lines works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Wooden rafters’ installation works completed and Primary Polishing works for Marble flooring completed. 19th to 22nd floor internal doors fixing works in progress. 18th to 20th copper piping works in progress. Handovers in progress. 1st coat external paint completed.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area, Basement & Clubhouse Updates
CLUB HOUSE: Swimming pool deck area granite works completed. 3rd floor badminton court HVAC ducts installation works in progress. 3rd floor squash court false ceiling works in progress. Staircase 1 & 2 railing works 95% completed. Ground floor banquet hall tiling works 95% completed. Terrace level toilets tiling works completed. North, East & West side glass fixing works in progress. External texture completed all sides. EXTERNAL: Banquet Lawn area works completed. Towers A west side Landscaping & Plantations works in progress. Towers D East side Landscaping & Plantations works in progress. Tower A & D around landscaping and plantations works completed. South side landscaping and plantations works completed. All sides boundary wall texture works completed.
Tower A
Tower B
Tower C
Tower D
Clubhouse and Common Area
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Entrance lobby glass works in progress.17th to 18th floors door fixing ,19th to 22nd floors kitchen dado tiling works,15th floor copper piping works in progress. Talk back installations completed in all the floors. External paint final coat works in progress.1st to 10th CS inspections and flat handovers in progress.11th to 15th Final finishes works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
8th floor slab casting completed & 9th floor in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
22nd floor & Terrace level slab casting works in progress. 5th Floor tiling works in progress. 5th floor CPVC Lines works and PVC Hanging lines works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Entrance lobby glass works in progress.17th to 18th floors door fixing, 15th to 21st floors copper piping ,15th floor kitchen granite works in progress. 1st to 10th CS inspections and flat handovers in progress.11th to 15th Final finishes works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Clubhouse and Common Area Update
CLUB HOUSE: North & East sides plastering and texture completed, South side plastering completed and texture in progress, West side plastering works in progress. 2nd floor HVAC indoor units installations and 3rd floor badminton court HVAC ducts installation works in progress. B1 to Ground floor staircase 2 granite works in progress. BASEMENTS: Surface drain finishing works completed and Basements VDF groove cutting and sealant filling completed. EXTERNAL :Tower D west side podium waterproofing works in progress, Cobble stone works in progress and east side boundary wall texture and paint works in progress. North side podium slab works in progress.
Tower A
Tower B
Tower C
Tower D
Clubhouse and Common Area
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower A Update
Entrance lobby false ceiling works completed & false ceiling board fixing works in progress.Door fixing 16th & 17th floor,copper piping 12th to 18th floor works in progress. Final finishing 3rd to 10th floors completed & cleaning in progress.Kitchen granite 13th to 18th floor works in progress.Entrance lobby false ceiling works completed & false ceiling board fixing works in progress.Door fixing 16th & 17th floor,copper piping 12th to 18th floor works in progress. Final finishing 3rd to 10th floors completed & cleaning in progress. Kitchen granite 13th to 18th floor works in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower B Update
Slab casting 1st to 6th floor completed & 7th floor in progress.
TS RERA Number: P02400003069
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Update
20th & 21st Slab casting completed. CPVC lines & PVC hanging lines works in progress and Tiling works 3rd & 4th floor works in progress.