A thoughtfully designed, high-rise community of 1,361 homes situated a few minutes away from the IT District.
One City is located in Kukatpally on the KPHB - HITEC City main road with convenient access to the best of retail destinations, schools and hospitals. The project comprises 2 & 3 bedroom apartments spread across 5 towers that soar between 28 to 33 floors into the sky.
1,208sft to 1,740sft
Vaastu Compliant
42,000 sft Clubhouse
Ready to move in units
Under construction units
INDIS PropCare Services
No Common Walls
Access to the Main Road
Windward Facing Towers
Vehicle-free Podium
Designed to maximise sunlight
Get In Touch
spotlight apartment units
01
02
Corner Apartments Scheduled for Handover.1,735sft, West Facing 3BHK Apartments. Limited Inventory, Hurry!
Starting at ₹47 Lakhs
ONE CITY, HYDD-01
Kukatpally
02
02
1,216sft, West Facing 2BHK Apartments. Perfect for a small Nuclear Family.Located near HITEC City & Kukatpally.
Starting at ₹41 Lakhs
ONE CITY, HYDE-04
Kukatpally
Unlock all 2 Spotlight floorplans
Location
Kukatpally
KPHB-HITEC City Main Road, Kukatpally, HYD, Telangana — 500072
Early warning heat detectors in your kitchen. Multi-detectors for heat and smoke in all the remaining rooms.
Detectors trigger an early warning fire alarm alerting residents and personnel in the building with the location of a potential fire.
Smoke and Heat Detector
Every floor has early warning fire measures like hand-held extinguishers and water hoses.
In case a fire is too intense for early warning fire measures, follow the exit signs and evacuate the building.
A pressurized network of pipes feed the fire sprinklers in every room of your house.
Every fire sprinkler has a temperature activated glass bulb that melts at 68° Celsius.
Only the fire sprinklers in the region of the fire will activate when a fire melts the glass bulbs.
Temperature Activated Sprinkler
Three redundant water pumps activate in sequence when they sense a drop in water pressure. This ensures the sprinklers are fed with a constant water pressure.
Pump 1 is an electric pump capable of delivering 180 litres per minute.
Pump 2 is a high capacity electric pump which can deliver up to 2250 or 2850 litres per minute, depending on the height of the building. This pump switches on if Pump 1 is unable to maintain water pressure.
Pump 3 is a high capacity diesel pump which can also deliver up to 2250 or 2850 litres per minute, depending on the height of the building.
This diesel pump switches on if Pump 1 and 2 are unable to maintain water pressure or if the electrical power supply fails.
68°celsius
will melt the temperature activated glass bulb and active the sprinkler.
Engineering
The engineering that ensures your water comes to you at the right quality and pressure.
Treatment and reuse of Sewage Water drops the overall quantity of water needed by a factor of 40.9%.
Metered water usage on an apartment level reduces water consumption patterns.
Low flow, water-efficient fixtures imitate the flow characteristics of regular fixtures while using 30% less water.
Pneumatic Booster Pumps actively boost water pressure to the upper floors.
Pressure Reducing Valves are passive mechanisms that reduce water pressure across lower floors.
Pressure Reducing Valve
Construction
Updates
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
March 2020
February 2020
January 2020
December 2019
November 2019
October 2019
Tower D
Tower E
Tower D Updates
Terrace slab casting is completed | 27th floor block work is in progress | 24th floor plastering work is in progress | 11th and 12th floor waterproofing works are in progress | 5th and 5th floor flat putty works are in progress | 11th floor door frame works are in progress.
Tower E Updates
External wall texture works are in progress | Toilet floor works are in progress on 26th floor | Grouting works are in progress on 18th floor | Acid wash is completed upto 18th floor | Door polishing and lock works are in progress on 20th and 25th floors respectively.
Tower D
Tower E
Tower D Updates
Terrace slab work is in progress | 24th floor block work and 21st floor plastering works are in progress | Waterproofing works are in progress from 5th to 9th floors.
Tower E Updates
External texture works are about to complete | 23rd floor toilet floor works are in progress | Flooring works are in progress at 9th series flats on 24th and 25th floors | Door lock works are in progress on 22nd floor | fire NOC inspection is completed.
Tower D
Tower E
Tower D Updates
32nd floor slab casting work is in progress | 24th floor block works are in progress | 21st floor plastering works are in progress | Waterproofing works are in progress from 5th to 9th floors.
Tower E Updates
External texture works are in progress | Floor protection works are in progress on 30th floor | Main door polishing and lock fixing works are in progress | Terrace waterproofing works are in progress | Block works for all floors have been completed.
Tower D
Tower E
Tower D Updates
31st floor slab casting work is in progress | 20th floor block works are in progress | 19th floor plastering works are in progress.
Tower E Updates
External texture works are in progress | Floor tiles works are completed till 30th floor and protection works are in progress | Main door polishing works are in progress on 1st and 13th floors | Terrace and podium water proofing works are in progress | Block works at ground floor and basement are in progress | Lift Machine Room (LMR) drive motors and electrical panel installation is completed.
Tower D
Tower E
Tower D Updates
30th floor slab casting is in progress | 17th and 18th floor block works are in progress | 15th floor plastering works are in progress.
Tower E Updates
Toilet water proofing is completed till 30th floor | Toilet tiles works are in progress on 29th and 30th floors| Floor works are in progress on 28th, 29th and 30th floors | Main door polishing works are in progress on 1st and 11th floors | Main door locks are getting installed on 16th floor | Blockworks are in progress at ground and basement level | Terrace & podium water proofing is in progress | Electrical works of passenger lifts 1, 2 and 3 are in progress.
Tower D
Tower E
Tower D Updates
27th floor slab casting work is in progress | 10th and 11th floor block works are in progress | 9th floor plastering works are in progress.
Tower E Updates
External texture works are in progress | 30th floor toilet waterproofing work are in progress | 20th to 27th floor tiles and tiles protection works are in progress | Ground floor and basement plastering works are in progress | Terrace waterproofing works are in progress.
Tower D
Tower E
Tower D Updates
24th floor slab works are in progress | 10th and 11th floor block works are in progress | 9th floor plastering works are in progress.
Tower E Updates
Terrace slab works are completed | 30th floor toilet water proofing works are in progress | Toilet tiles works are in progress on 20th and 27th floors | Firefighting works are in progress at basement | LMR (Lift Machine Room) motors and electrical panels installation works are completed | Lift door works are in progress.
Tower D
Tower E
Common Area
Tower D Updates
21st floor slab casting work is in progress.
Tower E Updates
Terrace slab casting is completed | Ground floor block works are in progress | Ground floor and 30th floor plastering works are in progress | Waterproofing works are in progress on 26th and 27th floors | Toilet tiles works are in progress on 16th and 20th floors | Basement firefighting works are in progress | Service Lift Machine room waterproofing works are in progress.
Common Area Updates
Ladies corner cobblestone laying works are completed at podium area | Banquet lawn landscaping and granite works are completed.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
Grouting works are completed upto 32nd floor | Ground floor deep cleaning works are in progress | Door polishing works are in progress at ground floor | Grid ceiling works are completed upto 32nd floors | Wiring & switch board fixing is completed upto 32nd floor.
Tower D Updates
17th floor slab works are in progress.
Tower E Updates
Terrace slab works are in progress | 29th floor block works are in progress | 28th floor plastering works are in progress | Toilet waterproofing is completed till 22nd floor | 14th floor toilet tile works are in progress |Internal flat flooring works are in progress on 14th floor |Pelmet works are in progress from 2nd to 5th floors |Fire fighting works are in progress at basements | Piped gas connection works are completed upto 16th floor | Service & passenger lift machine room de-shuttering works are in progress.
Clubhouse Updates
Swimming pool is handed over to PropCare | Cobble stone work at the podium ladies corner is completed | Banquet lawn landscaping works are in progress.
Tower C
Tower D
Tower E
Clubhouse & Common Area
Tower C Updates
32nd floor tile grouting is completed | Ground floor deep cleaning is in progress | Grid ceiling is completed till 32nd floor.
Tower D Updates
14th floor slab casting is in progress.
Tower E Updates
Terrace slab casting works are completed | LMR slabs casting is in progress | 28th floor block works are completed and plastering works are in progress | 12th floor toilet tiling works are completed |Piped gas connection works are in progress on 15th floor.
Clubhouse & Common Area Updates
Swimming pool commissioning is completed | Cobble stone lying is completed at podium ladies corner | Banquet lawn landscaping work is in progress.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
30th floor wiring works are completed and switch board works are in progress | Deep cleaning is in progress on 30th floor |Tile grouting, door polishing and grid ceiling works are completed on 32nd floor.
Tower D Updates
10th floor slab casting completed.
Tower E Updates
Electrical wall conduiting is completed from 1st to 18th floors | 2nd, 3rd and 5th floor flat tiling works are completed | Tile protection works are in progress | 4th, 6th and 8th floor flooring works are in progress | Water proofing works are in progress from 15th to 21st floors | 25th floor plastering work is completed | 27th and 28th floor block works are in progress | Terrace slab casting completed.
Clubhouse Updates
Swimming Pool final commissioning is in progress |Banquet Hall has been handed over to PropCare | Ladies corner cobble stone laying work is in progress | Banquet Lawn granite works are in progress.
Tower C
Tower D
Tower E
The Square Clubhouse
Tower C updates
Tile Grouting is in progress at the 31th Floor while at the 28th Floor, deep cleaning and wiring plus switch board fixing is in progress | from the 1st to the 15th Floor, the fire alarm, detection system and public address system, internal cable pulling is completed and is in progress till the 21st Floor.
Tower D updates
Structure casting of the 8th Floor is completed and that of the 9th Floor in progress.
Tower E updates
Terrace Floor rebar and shuttering works in progress | Plastering on Floors 21 and 22 are in progress | Flooring on the 2nd Floor are in progress | Piping works are in progress on the 15th,19th, 23rd, 24th and the 25th Floors, ressure testing is in progress on the 13th and 21st Floors and the final welding works are in progress on the 14th, 16th, 17th, 19th, 23rd and the 24th Floors | Wall Conduiting are completed from Floors 1st to 14th and in progress on the 15th Floor, chasing is completed from floors 1st to 14th and is in progress on the 15th Floor.
The Square Clubhouse updates
Entrance glass door fixing and SS Railing completed | Swimming Pool epoxy grouting completed | Banquet Hall completed.
Tower C
Tower D
Tower E
The Square Clubhouse
Tower C Updates
30th floor grouting works are in progress | 27th floor deep cleaning works are in progress | 28th floor door polishing works are in progress | Grid ceiling works are completed from the 1st to 32nd floors and the same is in progress at ground floor | 27th floor switch board works are in progress.
Tower D Updates
6th floor slab casting is completed | 7th floor slab casting works are in progress.
Tower E Updates
28th floor slab casting is completed | 29th floor slab rebar and shuttering works in progress |22nd and 23rd floors block works are in progress | Plastering works are in progress on the 20th and 21st floors | Toilet water proofing works are in progress on the 5th, 6th, 7th and 8th floors | Fire fighting works are in progress on the 12th, 15th, 16th and 21st floors.
Clubhouse Updates
Façade cleaning is completed | Entrance glass door fixing is completed | Swimming pool tile works and grouting works are completed | Pool deck area painting works are completed | Banquet hall false ceiling works are in progress | Clubhouse south side pavers works are in progress.
Tower C
Tower D
Tower E
The Square Clubhouse
Tower C Updates
Wiring and switch fixing works are in progress at 27th floor |Grid false ceiling work is in progress at 28th floor | Sliding doors fixing works are completed till 32nd floor | Deep cleaning work is in progress at 27th floor | Cobble stone works are completed between Clubhouse and Tower C | Polishing works are in progress at 27th floor.
Tower D Updates
4th floor slab casting is completed | Flats shuttering and steel works are in progress at 4th and 5th floors | Gas bank doors and ventilators fixing works are completed.
Tower E Updates
26th floor slab casting is completed | Slab steel works is in progress at 27th floor | Wall, slab steel and shuttering works are in progress at 25th and 26th floors | Bedroom and toilet door frames fixing is in progress at 13th floor | Waterproofing surface preparation and coating works are in progress at 2nd floor | Ledge wall and plastering works are completed at 2nd floor.
Clubhouse Updates
2nd coat of painting is completed at cafeteria, entrance lobby ceiling area |Entrance glass door works for stair case and lift lobbies are completed | 2 coat of painting, column cladding and false ceiling works are completed at pool deck area | Water post ponding test and dewatering works are completed at pool area | False ceiling and light fixing works are in progress at outdoor area | North west side Texture work is in progress at Northwest side.
Tower C
Tower D
Tower E
The Square Clubhouse
Tower C Updates
Polishing works are in progress at 25th and 26th floors | Floor Grid false ceiling work is in progress at 24th floor | Sliding door fixing is completed up to 32nd floor | Grouting works are in progress at 29th floor | Gas bank plastering works are in progress
Tower D Updates
2nd floor slab casting is completed | 3rd floor slab casting works are in progress | Wall steel and shuttering work in progress at 2nd and 3rd floors
Tower E Updates
Block work and curing works are in progress at 11th to 15th floors | Plastering and curing works are in progress at 11th floor | Main door and bed room door frame works are in progress at 11th floor | 23rd floor walls and slab works are completed | 23rd to 24th FLOOR-3&8, 4&7 Slab steel works are in progress at 23rd and 24th floors
Clubhouse Updates
2nd coat of painting work is completed at cafeteria lobby ceiling | Glass door works are completed at entrance lobby | 2nd coat of painting, column cladding and false ceiling works are completed at pool area | Water post ponding test is in progress at pool area | Washroom works of all floors are completed| Salon interior works are in progress | Ceiling painting work is in progress at indoor game area | Gym, yoga room and day care centers are ready for handover | Squash and badminton courts are ready for handover | False ceiling and light fixing works are in progress at common area |
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
Granite fixing work is in progress at 32nd floor | Wiring and switch socket fixing works in progress at 23rd and 25th floors | Grid false ceiling work is in progress at 22nd floor | Sliding door work is in progress at 31st floor | Deep cleaning is completed at 23rd floor |Polishing works are in progress at 24, 25 and 26th floors | Grouting work is completed at 26th floor | Cobble stone work in progress near entrance area.
Tower D Updates
Slab work lobby beams works are in progress at 2nd floor | Slab steel work at unit 7 is in progress at 2nd floor | Slab shuttering work of units 2 and 6 are in progress at 2nd floor.
Tower E Updates
Block work and curing works are in progress from 7th to 10th floors | Plastering and curing works are in progress from 2nd to 5th floors | Main door and bedroom door frame works are completed from 2nd to 5th floors | Wall shuttering and steel works are in progress at 21st and 22nd floors.
Clubhouse And Common Area Updates
2nd coat painting is completed at cafeteria and entrance lobby ceiling | Entrance glass door works are completed for stair case and lift lobby areas | Water proofing work is in progress at pool area | Painting, column cladding and false ceiling works are completed at pool deck area | Sanitary fixtures fixing works are in progress at toilet area | Staircase railing and light fixing works are completed | Salon interior works are in progress |Painting works are in progress at indoor games area | Gym, yoga room, squash court and day care center are ready for handover | False ceiling and light fixing works are in progress at the banquet hall | Vinyl flooring work is in progress at badminton courts.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
Cobble stone works are in progress at south side of the tower | 1st coat of painting is in progress at 32nd floor | Wiring and switch socket works are in progress at 19th floor | Grid false ceiling and deep cleaning works are completed at 17th floor.
Tower D Updates
Slab works for units 1, 4, 5 and 7 are completed at 1st floor | Slab shuttering works are in progress at ground floor | Lobby beam’s steel works are in progress at 2nd floor.
Tower E updates
Slab casting is completed at 19th floor for all flats |Slab casting and steel works are in progress at 20th floor | DPC and curing works are in progress at 8th floor | Block work and curing works are in progress at 7th floor.
Clubhouse Updates
2nd coat of putty work is completed at cafeteria area | Column cladding works are in progress at pool area | Dado, flooring and door fixing is completed at washroom area | Cladding completed and false ceiling works are in progress at lift area | Floor works are completed at daycare and indoor game area | Entrance glass door completed | Vinyl flooring and glass partition works are in progress at gym and yoga room | Painting and light works are in progress at the banquet hall | Painting work is in progress at the badminton court.
Tower C
Tower D
Tower E
Clubhouse
Common Areas
Tower C Updates
Handover process is in progress |Car parking marking at basement 2, 3 and 4 are in progress | Screed concrete works are completed in basement 1 | Door polishing works are completed upto 15th floor | 1st coat of painting is completed upto 29th floor.
Tower D Updates
Ground floor slab work is completed | Second floor lobby slab shuttering work is in progress.
Tower E Updates
Slab work is completed upto 16th floors | Slab casting of units 1, 2, 5, 6, 9 and 10 are completed at 17th floor.
Clubhouse progress
ACP finishing works are in progress | Glass installation works are completed, texture works are in progress | Ground floor false ceiling works are completed | Tiling works are completed in all floors.
Common Area Updates
Deep cleaning works at the pools area are in progress | Changing rooms are ready for handover | Pavers and cobble stone works are completed around Tower C.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
Hand over process started | 32nd floor toilet dado works are in progress | Flooring works are in progress at 31st floor | Door shutter fixing works are in progress at 27th floor.
Tower D Updates
Ground floor is completed | First floor shuttering and reinforcement works are in progress.
Tower E Updates
Slab casting work is completed upto 14th floor.
Clubhouse updates
External glazing frame fixing work is completed | Glass fixing work is in progress |Flooring works are in progress | Toilet dado and flooring works are completed.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
Terrace water proofing work is completed |External texture work is in progress | Waterproofing works are in progress at 30th floor | Toilet dado works are in progress at 29th floor | Flooring works are in progress at 29th floor | Door shutter fixing is in progress at 20th floor.
Tower D Updates
Ground floor slab casting work is completed.
Tower E Updates
Slab casting work is completed at 12th floor.
Clubhouse Updates
External glazing, frame fixing works are completed |Glass fixing works are in progress |Flooring works are in progress | Toilets dado and flooring works are in progress | Badminton court and Squash court works are in progress | Swimming pool is ready and inaugurated for the use of residents.
Tower C
Tower D
Tower E
Clubhouse
Tower C Updates
External texture work is in progress | Waterproofing works are in progress at 26th floor | Toilet flooring works are in progress at 24th floor | Flooring works are in progress at 21st floor | 2nd coat putty works are in progress at 32nd floor.
Tower D Updates
Basements 1, 2, 3 and 4 are completed | Ground floor shuttering works are in progress.
Tower E Updates
Slab casting works are in progress 11th floor.
Clubhouse Updates
Truss work is in progress | External glazing frame fixing is in progress | Flooring work is in progress at 1st floor | Dado and flooring works are in progress at ground floor toilets.