A thoughtfully designed, high-rise community of 1,361 homes situated a few minutes away from the IT District.
One City is located in Kukatpally on the KPHB - HITEC City main road with convenient access to the best of retail destinations, schools and hospitals. The project comprises 2 & 3 bedroom apartments spread across 5 towers that soar between 28 to 33 floors into the sky.
1,208sft to 1,740sft
Vaastu Compliant
42,000 sft Clubhouse
Ready to move in units
Under construction units
INDIS PropCare Services
No Common Walls
Access to the Main Road
Windward Facing Towers
Vehicle-free Podium
Designed to maximise sunlight
Get In Touch
Location
Kukatpally
KPHB-HITEC City Main Road, Kukatpally, HYD, Telangana — 500072
Early warning heat detectors in your kitchen. Multi-detectors for heat and smoke in all the remaining rooms.
Detectors trigger an early warning fire alarm alerting residents and personnel in the building with the location of a potential fire.
Smoke and Heat Detector
Every floor has early warning fire measures like hand-held extinguishers and water hoses.
In case a fire is too intense for early warning fire measures, follow the exit signs and evacuate the building.
A pressurized network of pipes feed the fire sprinklers in every room of your house.
Every fire sprinkler has a temperature activated glass bulb that melts at 68° Celsius.
Only the fire sprinklers in the region of the fire will activate when a fire melts the glass bulbs.
Temperature Activated Sprinkler
Three redundant water pumps activate in sequence when they sense a drop in water pressure. This ensures the sprinklers are fed with a constant water pressure.
Pump 1 is an electric pump capable of delivering 180 litres per minute.
Pump 2 is a high capacity electric pump which can deliver up to 2250 or 2850 litres per minute, depending on the height of the building. This pump switches on if Pump 1 is unable to maintain water pressure.
Pump 3 is a high capacity diesel pump which can also deliver up to 2250 or 2850 litres per minute, depending on the height of the building.
This diesel pump switches on if Pump 1 and 2 are unable to maintain water pressure or if the electrical power supply fails.
68°celsius
will melt the temperature activated glass bulb and active the sprinkler.
Engineering
The engineering that ensures your water comes to you at the right quality and pressure.
Treatment and reuse of Sewage Water drops the overall quantity of water needed by a factor of 40.9%.
Metered water usage on an apartment level reduces water consumption patterns.
Low flow, water-efficient fixtures imitate the flow characteristics of regular fixtures while using 30% less water.
Pneumatic Booster Pumps actively boost water pressure to the upper floors.
Pressure Reducing Valves are passive mechanisms that reduce water pressure across lower floors.
Pressure Reducing Valve
Construction
Updates
February 2024
January 2024
December 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
March 2020
February 2020
January 2020
December 2019
November 2019
October 2019
ONE CITY
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
ONE CITY Update
From a construction perspective, all works have now been completed with residents ready to use the provided amenities and facilities.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D update
Handovers in progress. Landscaping works and Podium level plantations works completed.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D update
Entrance lobby marble flooring cleaning works completed and unit wise numberings completed in all floors. Entrance lobby ramp works ,handovers ,landscaping and plantations in progress.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D update
In progress are the entrance lobby ramp & flooring, putty buffering, balcony tiling, internal painting, door polishing, external texture, podium cobblestone laying alongwith car parking number works that are almost completed.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
In progress are the entrance lobby marble flooring, 25th floor corridor kota stone polishing, 1st coat of internal painting (on the 25th floor), podium cobble stone laying and the car parking numbering in the basement. For both Basement 1 & 2, the entrance glass and lift lobby painting works are now completed.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Entrance lobby block work with texture, granite works for the steps and the fundermax work is completed in the entrance lobby. Apartment internal works are in progress while the corridor tiling is completed till the 3rd floor. In the basement, the car parking numbering works are in progress.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Entrance lobby block work is in progress, while the fundermax work is completed in the entrance lobby and the podium cobble stone works are in Progress. In the basement, the car parking numbering is in progress while the numbering for the guest parking is completed along with the lift lobby painting. Passenger lift wotrks are in progress whereas the service lift is operational.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
2nd coat of the External Painting is in progress. Water proofing works are almost complete and UPVC sliding doors fixing is in progress.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Water proofing works are almost complete. 2nd Coat of putty is completed till the 32nd floor. UPVC sliding doors fixing is in progress and is completed for Windows. The Service Lift is operational and the passenger lifts work is in progress.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Water proofing works are in progress. Floor tiling is in progress on the 26th floor. Door Shutters Fixing of the main as well as internal doors is under progress on the 22nd floor. UPVC windows fixing is in progress on the 29th floor and sliding doors fixing is in progress on the 26th floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Update
Piped gas activation in flats are in progress along with FDS system inspection.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Putty 2nd coat is completed, floor tiling till the 28th floor is completed. Door Frames Fixing is in progress on the 2nd floor but is completed from the 3rd floor till the 32nd floor. Door Shutters Fixing of the main as well as internal doors is completed from the 4th floor till the 21st floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Update
For the Piped gas system, the piping installation works along with welding works from the Basement (1 level) till the 30th floor are completed. Installation of gas meters and accessories is completed in 287 apartments (out of a total of 298 apartments).
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Water proofing works are completed till the 32nd floor. For the FPS (Fire Protection System) works in the basement are in progress. | 2nd coat of putty till the 32nd floor is completed, flooring is completed till the 25th floor, Door frames fixing is completed and balcony railings fixing are completed till the 23rd floor. | External texture works on the North and South side are complete as for the East and West side are in progress.
Tower D
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Water proofing works are completed till the 31st floor. Terrace signage has been installed. For the FPS (Fire Protection System) Final welding works completed from basement 4 to 18th floor. | Door frames fixing is in progress on the 32nd floor and floor tiling works are completed till the 24th floors.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Update
Works of the terrace slab, above Terrace and MS staircases are completed. Texture works for external painting is completed on the North side and is in progress for the other 3 sides. Blacony railing fixing is going on the 17th floor. For the FPS (Fire Protection System) Final welding works of the header and branch line works in basements 3& 4 are in progress. While works are in progress in basements 1 & 2. | Putty (2nd coat) is completed till from the 4th till the 32ndfloor, door frames fixing from the 5th till the 31st floors are completed and floor tiling works are completed in floors 4th, 5th and from the 9th till the 22nd floors.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Update
Piping installation along with welding works for the Piped Gas System from Basement 1 to the 30th is completed. Gas meters and accessories are installed in 259 flats out of 298 flats. Entrance Lobby Texture paint and landscaping works on the South & East sides is completed.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D update
Tower external surface preparation for painting works including texture works are almost completed and other tower works like lifts, fire system, blockwork, plastering, putty, balcony railings fixing etc. works are in progress. For further details, please contact our Customer Service Manager.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E update
Tower external texture is completed and other tower works like piped gas system etc. works are in progress. For further details, please contact our Customer Service Manager.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
LMR works are in progress above terrace level | 32nd floor blocks are in progress | 31st floor plastering is in progress | Water proofing works are in progress on 20th and 21st floors | 1st coat of putty works is in progress on 31st floor | 2nd coat of putty works is in progress on 25th floor | 21st Floor door frame works are in progress | Balcony railing works on 16th floor are in progress | Floor tiling works are in progress on 6th and 13th floors.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture walls are almost completed | Grouting and acid wash works are completed on all floors | 28th floor Pelmet works are in progress | 28th floor door polishing works are in progress | Internal door lock works on 25th floor are in progress.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
Terrace and LMR slab works are completed | 30th floor block works are in progress | 28th floor plastering works are in progress | 15th and 17th floor water proofing works are in progress | 26th floor putty works are in progress | 15th floor door frame works are in progress | Flooring works are in progress on 9th floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture work is almost completed | 30th floor toilet grouting is in progress | Floor works are in progress on 25th floor | Deep cleaning is completed till 25th floor | Door polishing is completed till 24th floor | 25th floor door lock works are in progress | Gas pipe installation is completed till 30th floor | Lifts are operational | Entrance lobby flooring and glass works are completed.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
Terrace slab casting is completed | 27th floor block work is in progress | 24th floor plastering work is in progress | 11th and 12th floor waterproofing works are in progress | 5th and 5th floor flat putty works are in progress | 11th floor door frame works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External wall texture works are in progress | Toilet floor works are in progress on 26th floor | Grouting works are in progress on 18th floor | Acid wash is completed upto 18th floor | Door polishing and lock works are in progress on 20th and 25th floors respectively.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
Terrace slab work is in progress | 24th floor block work and 21st floor plastering works are in progress | Waterproofing works are in progress from 5th to 9th floors.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture works are about to complete | 23rd floor toilet floor works are in progress | Flooring works are in progress at 9th series flats on 24th and 25th floors | Door lock works are in progress on 22nd floor | fire NOC inspection is completed.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
32nd floor slab casting work is in progress | 24th floor block works are in progress | 21st floor plastering works are in progress | Waterproofing works are in progress from 5th to 9th floors.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture works are in progress | Floor protection works are in progress on 30th floor | Main door polishing and lock fixing works are in progress | Terrace waterproofing works are in progress | Block works for all floors have been completed.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
31st floor slab casting work is in progress | 20th floor block works are in progress | 19th floor plastering works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture works are in progress | Floor tiles works are completed till 30th floor and protection works are in progress | Main door polishing works are in progress on 1st and 13th floors | Terrace and podium water proofing works are in progress | Block works at ground floor and basement are in progress | Lift Machine Room (LMR) drive motors and electrical panel installation is completed.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
30th floor slab casting is in progress | 17th and 18th floor block works are in progress | 15th floor plastering works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
Toilet water proofing is completed till 30th floor | Toilet tiles works are in progress on 29th and 30th floors| Floor works are in progress on 28th, 29th and 30th floors | Main door polishing works are in progress on 1st and 11th floors | Main door locks are getting installed on 16th floor | Blockworks are in progress at ground and basement level | Terrace & podium water proofing is in progress | Electrical works of passenger lifts 1, 2 and 3 are in progress.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
27th floor slab casting work is in progress | 10th and 11th floor block works are in progress | 9th floor plastering works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
External texture works are in progress | 30th floor toilet waterproofing work are in progress | 20th to 27th floor tiles and tiles protection works are in progress | Ground floor and basement plastering works are in progress | Terrace waterproofing works are in progress.
Tower D
Tower E
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
24th floor slab works are in progress | 10th and 11th floor block works are in progress | 9th floor plastering works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
Terrace slab works are completed | 30th floor toilet water proofing works are in progress | Toilet tiles works are in progress on 20th and 27th floors | Firefighting works are in progress at basement | LMR (Lift Machine Room) motors and electrical panels installation works are completed | Lift door works are in progress.
Tower D
Tower E
Common Area
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
21st floor slab casting work is in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
Terrace slab casting is completed | Ground floor block works are in progress | Ground floor and 30th floor plastering works are in progress | Waterproofing works are in progress on 26th and 27th floors | Toilet tiles works are in progress on 16th and 20th floors | Basement firefighting works are in progress | Service Lift Machine room waterproofing works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Common Area Updates
Ladies corner cobblestone laying works are completed at podium area | Banquet lawn landscaping and granite works are completed.
Tower C
Tower D
Tower E
Clubhouse
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Updates
Grouting works are completed upto 32nd floor | Ground floor deep cleaning works are in progress | Door polishing works are in progress at ground floor | Grid ceiling works are completed upto 32nd floors | Wiring & switch board fixing is completed upto 32nd floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
17th floor slab works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
Terrace slab works are in progress | 29th floor block works are in progress | 28th floor plastering works are in progress | Toilet waterproofing is completed till 22nd floor | 14th floor toilet tile works are in progress |Internal flat flooring works are in progress on 14th floor |Pelmet works are in progress from 2nd to 5th floors |Fire fighting works are in progress at basements | Piped gas connection works are completed upto 16th floor | Service & passenger lift machine room de-shuttering works are in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Clubhouse Updates
Swimming pool is handed over to PropCare | Cobble stone work at the podium ladies corner is completed | Banquet lawn landscaping works are in progress.
Tower C
Tower D
Tower E
Clubhouse & Common Area
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower C Updates
32nd floor tile grouting is completed | Ground floor deep cleaning is in progress | Grid ceiling is completed till 32nd floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower D Updates
14th floor slab casting is in progress.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Tower E Updates
Terrace slab casting works are completed | LMR slabs casting is in progress | 28th floor block works are completed and plastering works are in progress | 12th floor toilet tiling works are completed |Piped gas connection works are in progress on 15th floor.
* These are randomly clicked pictures of work in progress from preceding month. Not to be considered as progress in entirety.
Clubhouse & Common Area Updates
Swimming pool commissioning is completed | Cobble stone lying is completed at podium ladies corner | Banquet lawn landscaping work is in progress.